3.11 Prepare a Cost Estimate
  • Estimate the trail construction or renovation costs by determining the quantity and price of materials, labour, equipment, and administration.

  • Calculate the total length and type of trail construction according to the different techniques required; eg. some sections may need minimal clearing, while other require boardwalk construction.

  • Estimate the total and unit costs of materials such as lumber, culverts, tread surfacing, signs and printed information.

  • Modify the trail design details to reduce the cost of materials if required.

  • Estimate the cost of labour for trail clearing and the construction of bridges, boardwalks and other trail elements. Allow for differences of terrain, weather, transportation time and other delays.

  • Base labour estimates on a crew of 3 or 4, or as determined by the type of construction management planned. Assume one fore-person for each crew.

  • Estimate the costs of equipment purchase or rental. Estimate the costs of construction start-up, transportation, food and accommodation, as well as administrative costs such as construction supervision and management.